Volume: 24, Issue: 5 - 03/17/2026
The distinction between a subcontractor and a supplier of materials or equipment is sometimes blurred. Subcontractors perform construction work at the site. Suppliers have a more limited role at the site, typically delivering their product and sometimes installing it. The difference is more than semantic—it can affect rights to mechanic’s liens and payment bond coverage. It can also have an impact on licensing requirements.
A California company designed and furnished custom wine cellars. The general contractor discovered the company did not have a contractor license and attempted to use the unlicensed status to recoup payments it had made. The wine cellar company said it had merely installed the equipment it had delivered; however, a court ruled this was no “plug-and-play” situation.
The second case in this issue involves the authority of a project architect to block final payment after substantial completion and use and occupancy by the public project owner. The construction contract made architect approval a precondition to the final payment release, so the matter came down to the scope of the architect’s discretion.
The third case addresses a bid protest about a municipal project owner that mishandled procurement in a number of ways but showed no indication of favoritism or malintent. A Connecticut court expressed reluctance to impose its judgment and supersede the contract award decision of the municipality.
A subcontract called for improvements permanently affixed to a structure. This was not merely an equipment delivery—a contractor license had been required. The prime contractor did not lose its rights under the licensing statute when it terminated the subcontract for its own convenience.
The approval of a final payment application by the project architect was, under the terms of the contract, a prerequisite to release of final payment. The contractor could not use the state prompt payment statute to mandate release of payment, even though the project was certified substantially complete and was in use by the public.
Despite ambiguity in the specifications and the right for bidders to take exceptions to the specifications, a court would not supersede a municipality’s admittedly imperfect procurement process.
Volume: 24, Issue: 4 - 03/04/2026
The AIA General Conditions calls for designation of an “initial decision maker”—usually the project architect—to respond to disputes. The process leads to nonbinding mediation and binding arbitration, if necessary. But, can the initial decision become final and binding, a damage assessment to be confirmed in court, much like an arbitration award?
A Texas court recently rejected this argument. The decision, issued by the project architect, adopted a repair contractor’s pricing spreadsheet that was unsupported by documentation or expert opinion. It was not credible evidence. The contractor, regardless of the initial decision, had not lost the right to contest the owner’s damage claim.
The other case in this issue involved a state “insurance bad faith” statute that imposed punitive damages on insurers that demonstrated a lack of good faith in processing claims. The Pennsylvania Supreme Court was asked if the statute also applied to a construction contract payment bond surety that had refused to compensate an unpaid subcontractor.
The initial decision of a project architect was not, under the AIA General Conditions, final and binding with regard to the cost of corrective work required on a project. The contractor could challenge the decision in court, and a trial court should not have turned that amount into a judgment against the contractor and its performance surety.
A payment bond on a construction contract was not an insurance policy. The state insurance bad faith statute did not apply to the surety’s conduct. However, the surety was responsible for an arbitration award in favor of an unpaid subcontractor.
Volume: 24, Issue: 3 - 02/17/2026
Bids on public construction contracts are typically completed in the final minutes before bid submittal. Price quotations from trade subcontractors are not received until then, leaving no time to negotiate a subcontract agreement. The bidder on the prime contract relies on the subcontractor quote and, if awarded the prime contract, expects the sub to perform at that price.
An electrical subcontractor in Washington State tried to back out of its price quotation after bid opening. The sub’s proposal had stated that written acceptance was required within seven days of receipt. The bidder had not accepted in writing but had incorporated the price into its successful bid. The subcontractor argued that any reliance by the bidder had not been reasonable in light of the lack of acceptance.
The second case in this issue involves qualification to provide expert opinion regarding an architect’s professional standard of care. The South Carolina Supreme Court ruled that under state law, a professional engineer’s testimony would be acceptable. The engineer had chosen, however, to offer only an opinion regarding construction contract administration, not an architect’s professional design responsibilities.
The third case addresses commercial general liability (CGL) insurance coverage for subcontracted work. Under the terms of a contractor’s CGL policy, there was coverage only if the subcontract was in writing and the subcontractor had proof of its own CGL coverage.
Although a subcontractor price quotation stated it was conditioned on written acceptance within seven days of receipt by the bidder on a public contract, the price became binding on the sub despite the bidder’s lack of written acceptance.
A state statute required an affidavit from a qualified expert in order to proceed with a professional negligence action. The statute did not require the expert to possess the same professional license as the defendant.