Volume: 23, Issue: 24 - 12/31/2025
Wishing You a Happy, Healthy and Successful New Year! From the staff of WPL Publishing Company |
Disputes over contract claims can sometimes get personal. After all, it’s individuals—real people—who interact on behalf of their respective organizations. Things get said, attitudes are conveyed. A contractor recently sued an employee of the municipal project owner, an employee of the consulting engineer and an employee of the construction manager. The allegations were interference with contract and business conspiracy.
The aggrieved contractor failed to consider the law of agency. Agents acting within the scope of their duties have an identity of interest with their principal—in this case, the municipal project owner. As a Virginia court said, “Consultants and employees advising a municipal owner act as its agents, not as third-party intermeddlers.”
The other case in this issue involved a public project owner’s attempt to void contracts based on the owner’s own irregularities during the procurement process. The effect of the voided contracts would have been to deny the contractor payment for $811,000 of completed work. The project owner did not succeed in this effort.
A public project owner’s employee, outside consultants, and employees of the consultants were acting as the project owner’s agents when evaluating and responding to a contractor’s claim for delay damages.
Substantial, not strict, compliance with a public works procurement statute is required of public project owners.
Volume: 23, Issue: 23 - 12/16/2025
Liquidated damages for late completion are a contractually stipulated form of delay damages. And, recovery of duplicative damages is prohibited, as it provides a payment windfall in excess of actual damages. A prime contractor’s recovery from a defaulted subcontractor recently provided an interesting application of these principles.
The subcontract did not include a liquidated damages clause, but it did contain a “pass-through” provision—any liquidated damages assessed by the project owner against the prime contractor as a result of the subcontractor’s slow performance were the responsibility of the subcontractor. The subcontract also said the tardy sub would owe the contractor for “extended project overhead.”
The subcontractor argued that the liquidated damages pass-through and assessment for extended overhead amounted to double recovery. The contractor responded that the extended overhead constituted an element of delay damages distinct from the pass-through.
The second case in this issue involves the “cost of repair” measure of damages on a cost-plus contract. The defaulted contractor argued this was not a fixed-price contract where the owner received a defined project for a set price; rather, the owner was responsible for the cost of the work even if it was in need of repair.
The third case addresses the government’s sovereign act of closing access to a military base during the COVID-19 pandemic. While the contractor could not recover increased on-site costs from the government, questions arose about the increased costs of off-site work the contractor could have performed notwithstanding the closure.
A subcontract pass-through of liquidated damages assessed against the prime contractor was a separate element of damages from the contractor’s extended project overhead.
“Cost of repair” is a permissible measure of damages for defective work on a cost-plus contract. The owners reasonably expected workmanlike performance and should not be held responsible for the cost of remediation.
A contractor could not pursue a claim for increased on-site costs caused by denial of access to a base, but it could pursue claims for increased off-site costs and logistical costs when access was later granted.
Volume: 23, Issue: 22 - 12/01/2025
Bidders on public works contracts are regularly asked to submit additional documents with their bids. The number and complexity of these submissions increase with evolving procurement statutes and regulations. It’s not surprising that bidders start to think of them as “standard boilerplate”—the bid price is firm, but the other stuff can be cleaned up after bid opening. That may or may not be accurate.
In a recent New Jersey case, an appellate court upheld rejection of a low bid because the bid bond bore a date prior to the extended deadline for bid opening. Rejection of the second low bid was also upheld because the accompanying certificate of uncompleted work was pre-dated. In each case, the deviation was material and could not be waived. The information could not be corrected or supplemented after bid opening.
In the other case in this issue, the South Dakota Supreme Court addressed for the first time the need for expert opinion to support a project owner’s claims against design professionals and a specialty constructor.
A low bid was nonresponsive due to a bid bond that pre-dated the bid opening date. A second low bid was nonresponsive due to a certification of uncompleted work that similarly pre-dated the bid opening date.
Expert testimony was required to maintain claims against an architect, an engineer, and a specialty trade contractor. The project owner’s CEO did not qualify, as he was not a licensed design professional and had no experience in the trade work in question.