The statutory period for filing a mechanic’s lien cannot be extended by agreement of the project owner and contractor. When change orders were issued for that purpose, the change order work did not extend the filing deadline.
The federal Miller Act prohibits the prospective waiver of payment bond protection. Consequently, a no-damage-for-delay clause in a subcontract was unenforceable in a delay claim seeking the increased cost of labor furnished to the project.
The Construction Claims Advisor summary of this case is available to ConstructionPro Network members and includes:
- The citation for the case (case name, case number, and date filed)
- An overview of the case
- Background information about the case
- A summary of the ruling
- A summary of the court’s conclusion and the resulting outcome
- Editor's commentary
- A link to the complete PDF copy of the original opinion