ConstructionPro Week, Volume: Construction Advisor Today - Issue: 157 - 05/03/2012

Can Anything Be Done About Bid Shopping?

By Bruce Jervis

 

The practice of “bid shopping” is the bane of trade contractor existence. This occurs when a bidder on a prime contract obtains a price quotation from a trade contractor and uses that price in calculating its bid. Upon award of the prime contract, the contractor then “shops” the trade contractor’s price around, disclosing it to competitors and inviting them to beat it.

 

Critics of bid shopping say general contractors take unfair advantage of their economic leverage, frequently gained through public works expenditures, and harm projects by bringing in weak, low-ball performers. In the public sector, statutes have been enacted requiring more direct procurement of trade work or mandating the listing of selected trade contractors in prime contract bids.

 

In the absence of legislative intervention, however, there is little trade contractors can do to protect themselves. This was illustrated in a recent Florida case. A paving contractor included language in its proposal prohibiting disclosure of the price to third parties. The proposal said any such disclosure would constitute acceptance of the proposal and create a binding subcontract.

 

The low bidder on the public project used the paving contractor’s price in its bid, disclosed the price to a third party, and awarded the paving subcontract to a different company. The paving contractor had no recourse. The price proposal was an offer. An offeror cannot unilaterally dictate the form or manner of acceptance of its offer.

 

What is your opinion of bid shopping? Is it a legitimate competitive business practice or a predatory misuse of public works funds? If you consider the practice inappropriate, what practical steps can be taken to discourage it?

 

Featured in Next Week’s Construction Claims Advisor:

  • Anti-Indemnification Statute Protected All Construction Parties
  • Design Did Not Render Contract Performance Impossible
  • Timely Acceptance of Subcontractor Bid Questioned

 

Comments

 

Payback is a bitch for bid shoppers. I love sending them whacked out numbers but excluding something in the small print. They never read that stuff when a bid comes in at 10 minutes to bid time. Subs do have a way to play their games too! We're not poor defenseless little pee-ons!

Treat us fair and we'll respond with accurate, fair, and timely pricing. Shop us out and watch out on the next one!

KM

We like to require the list of proposed subs in our contractor's proposals, with contract language requiring a valid reason and approval to switch them out.

 

Well said Kurt, thank you...

 

Your right about the bid shopping. I believe its happened to me!

 

please post the case record for the contractor law case

 

One of the standard contracts we use on construction projects typically includes language to the effect that the contractor cannot assign / sub all or any part of the works without the prior written approval of the A/E. The contractor is also required to list all trade subcontractors and the prices included in their bid. In addition to the subbing of the contract being at the discretion of the A/E, the contractor has a deadline by which he must submit a request for change or substitution. If a prime contractor submits a request for substitution after this deadline, the A/E can reject as late automatically.I have found that this significantly helps trade subs to be protected from bid shopping. This is not to say that bid shopping does not and has not occurred here. On poorly formed and administered contracts, it is quite common.

 

We have discussed this topic many times in our local and national ASPE (American Society of Professional Estimators)conferences, and I present a seminar about it as well designed to teach subcontractors how to combat this unseemly practice, which has several faces - bid chiseling, bid beating, bid peddling, bid discounting - they all stink. ASPE's Canons of Ethics specifically prohibit this practice, but most of these activities are perfectly legal, making them tough to combat. Thanks for raising this important topic in this forum; the creation of awareness is our best tool to use against these practices.

 

Nothing can be unless legislation is enacted at the State level. Honesty will only make one starve and collusion will continue just as it has done for centuries. Just like larceny has been illegal thru laws, bid collusion can be solved through legislation ONLY. People will not solve it on their own honesty, so long as their are others doing it with larceny in their hearts, the balance will have to suck it up or lobby for legislation making it illegal

 

NO!!!..(to Daniel)
You do not ever want the state involved in private business practices. While bid shopping is a crappy way to conduct business, it is a lawful business practice nonetheless. We all compare prices on the internet v. brick and mortar stores, etc. Subs just need to learn not to tip their hand when bidding. Schematic drawings, rough bids, and contract language will put us on even footing with the primes.

 

Very Interesting topic...Nobody ever likes having their price shopped after a bid, but we all like to have "last look" with our GC clients. Why else we would take them to play golf, go out to fancy dinners, etc. Let's get real here people...protect yourself and be smarter than your competition.

 

Most people involved in construction are members of at least one professional society. Those societies should at least censure bid shoppers and list their names in the newsletters.

 

As a GC we don't use bids from subs who send them 10 minutes before our bid time. At 10 minutes before bid time there is not enough time for us to change our bid and update our sublist. Those subs sending their bids late are only wasting their time. Sometimes we may lose a job from this policy, but 99% of the time the savings would not make a difference in our overall bid.

 

No!!! To Shamus. In North Carolina, on publc funded, municipal and county supported work, GC's must list their major subs of choice on their bid and the state makes them stick to those they name. That cuts down on the BS that some GC's pull.
On private work you take your chances with the GC's being honest.
All public work in NC requres at least three bidders in each major area sub area (GC, Plbg, HVAC, Elec and sometimes FP) in order to open the bid packages for that trade. If there is only two bds then they hold them and advertise the bid and bid it again n 2 weeks.
The real problem n NC is the Federal bids for government work. Those bids go to a GC,and they don't have to list their subs in the bid and they get shopped by the GC's like bandits.

 

We are and architectural firm in California and we have the requirement of all subs of 1/2 of 1% of total must be listed. This has helped reduce shopping unless the general lists a sub who he knows will fail with the hope of getting a sub of his choice to fill the void. I am sure this happens. With the economy in its current condition we are seeing subs drop form 5% to 30% on many projects. We are spending much time in the sub change process which if adverserial takes weeks if not months to go thru with numerous hearing and discovery.

 

How about some version of the old 'Kill Fee' concept:
The bidder submits a hard number for their estimating
fee (i.e. $5,000) along w/their bid price. If the GC then
shops the bid and looks to award elsewhere, it will now cost them ($5,000) to do so - and suddenly the new 'low bid substitute' may no longer be 'low' anymore.....the original 'low bidder' is 'low' once again!

 

Naturally, the only type of sub that can sell this approach to a GC is one that the GC knows to be
consistently low-priced and thus worth the ($5,000)
decrease in the spread w/the second low bidder.

Interesting discussion here. I have had multiple experiences with having my organized and timely bids being "shopped" by a GC. Both on private and public projects.
Needless to say, it is very frustrating to have put in a huge amount of effort to produce a competitive number only to have it sold out from under me after the bid deadline. But the question is: why would I want to do business with an unethical GC?
I'm truly not interested. I assume he will "sell me out" at some point during the construction phase or try and screw me out of money elsewhere on the project.
It's been my routine that after discovering I've been "shopped" on a bid I contact all of my subs, sometimes as many as 6 or 8 and tell them what has occurred. In this manner the GC's reputation has been revealed as an unethical one and we can all keep that in mind for future bids.

 

Tar & feather is the first thing that comes to my mind.
How about a fine of 25% of the bid going to the shopped contractor.
If a complaint is filed freeze the award of the job, investigate, & if it can be proven pull the contract & give it to GC #2.
Any of these penalties would stop this practice. 
It costs thousands of dollars to prepare most bids. 
When we are low & assuming we are a reputable contractor we deserve to get the project.

 

Right now if they shop they get dropped. No more bids from me ever!!! 
The shoppers would be the first to go for their lawyers if right after the bids were opened the owner said," Gee, these bids are so close I think we are going to give everyone one more chance to give us their best & final offer."

I would also be interested in knowing the case cited or other similar cases found for either party.

 

I have been on both sides of the fence sub/prime and seen shopping pulled on numerous occasions. Our industry does not need additional regulations to deal with.

 

As several have already said, the contractors that shop need to be outed. If you can prove that they have shopped you call the president/owner of the firm and tell him how you feel. Some estimators are shopping and receiving kick-backs.

If the firm is willing to shop legitimate quotes they are probably doing other unethical practices as well and why would you want to take the risk of doing business with them.

We might consider using something other than the "lowest" bidder to award contracts. More appropriate woudl be the bidder closest to the average of all bids received.

 

Other than that, Mr. Mehrer et. al. have the right idea. 

Well as a GC we are up against similar actions on the part of some owners that we bid to (retail work). More important is the late reciept of sub bids on bid day. Some sub's say that the supply houses, particularly with the mechanical trades, do the same thing and hold out releasing their material quotes until the last minute. I wouldn't call it bid shopping but more accurately trying to determine if a quote received 10 minutes before bid time has the correct scope?? So in 10 minutes with numerous bids being faxed and emailed, we are supposed to list the sub's we intent to use complete the pricing, and relay via phone all the information required on the bid form. No way!!!!

 

The problem I see with comments above, mostly coming from subcontractors, is that subcontractors bidding on a certain project will not bid to every general. When I am bidding a public project, we need to find the subcontractor that is only going to bid to me. So Subcontractor "a" bids to every gc and is low, but subcontractor "b" bids only to me and has a lower price than "a", then I am considered a bid shopper, when in fact, I did nothing wrong.

 

Send out scope letters early in the process and pricing later

 

I feel that my company has been bid shopped. Knowing I own a ethical electrical contracting firm that does quality work... I dont know how to identify that is the intent of the Gc before I bid the job. How do defend against, and how do I know it occurred?

 

 

 

COMMENTS

I have been exploring for a bit for any high-quality articles or weblog posts in this kind of area .

Exploring in Yahoo I eventually stumbled upon this web site.

Studying this information So i'm satisfied to express that I have an incredibly excellent uncanny feeling I

discovered exactly what I needed. I most undoubtedly will make sure to do not disregard this

website and give it a look regularly.
Posted by: Grondin - Friday, October 25, 2013 10:05 AM


I think the admin of this web page is genuinely working hard in favor of

his website, because here every data is quality based information.
Posted by: Dalton - Friday, October 25, 2013 11:43 AM


wonderful issues altogether, you just won a logo new reader.

What would you recommend about your put up that you simply made a few days ago?

Any sure?
Posted by: Loera - Sunday, October 27, 2013 8:16 AM


Hi friends, how is everything, and what you want to say concerning

this article, in my view its really amazing designed for me.
Posted by: Varner - Sunday, October 27, 2013 1:39 PM


I know this if off topic but I'm looking into starting my own blog and was curious what all is required to get set up?

I'm assuming having a blog like yours would cost a

pretty penny? I'm not very web smart so I'm not 100% positive.

Any tips or advice would be greatly appreciated.

Thanks
Posted by: Beckham - Sunday, October 27, 2013 7:56 PM


Your method of telling all in this piece

of writing is genuinely fastidious, every one be able to

effortlessly know it, Thanks a lot.
Posted by: Bolick - Saturday, February 1, 2014 5:47 PM


Hi, yeah this article is in fact good and I have learned lot of things from

it regarding blogging. thanks.
Posted by: Willson - Saturday, February 1, 2014 8:00 PM


I have been browsing online more than three hours today, yet I never found any interesting article like yours.

It is pretty worth enough for me. In my opinion, if all site owners and bloggers made good content as you did, the web will be a lot more useful than ever before.
Posted by: Carrozza - Wednesday, February 5, 2014 9:37 PM


This post is worth everyone's attention. When can I find out more?
Posted by: Schimmel - Monday, February 24, 2014 5:27 AM


Hi, the whole thing iss goinng sound here and ofcourse every one is sharing facts,

that's really fine, keep up writing.
Posted by: Elisha - Friday, February 28, 2014 5:43 AM


whole body garcinia cambogia reviews Thanks for

the suggestions you have shared here. Another thing I would like to

state is that computer system memory needs generally go up along with advancements

in the technological innovation. For instance, as soon as new generations of processors are brought to the market, there

is certainly usually a corresponding increase in the type demands

of both the computer memory along with hard drive space.

This is because the software operated simply by these

processor chips will inevitably boost in capacity to make new technology.

garcinia cambogia reviews and side effects
Posted by: Millsaps - Saturday, March 1, 2014 1:26 PM


Inspiring story there. What happened after? Good luck!
Posted by: Candler - Monday, March 3, 2014 10:38 PM


Inspiring quest there. What happened after?

Good luck!
Posted by: Paredes - Tuesday, March 4, 2014 3:38 PM


I do not know whether it's just me or if everyone else encountering

issues with your blog. It looks like some of the written text on your posts

are running off the screen. Can someone else please provide

feedback and let me know if this is happening to them too?

This may be a issue with my web browser because I've had this happen previously.

Thank you
Posted by: Sisk - Tuesday, March 4, 2014 4:46 PM


I'm curious to find out what blog pltform you have been using?

I'm having some minor security issues with myy latest website

and I'd like to find something more safe. Do you have any suggestions?
Posted by: Burne - Wednesday, March 5, 2014 5:09 PM


What's up, just wanted too tell you, I liked this article.

It was inspiring. Keep on posting!
Posted by: Frederic - Thursday, March 6, 2014 1:17 AM


I am curious to find out what blog systm you have been utilizing?

I'm experiencing some small security problems with my latest site and I would like to find something more risk-free.

Do you have any recommendations?
Posted by: Clark - Thursday, March 6, 2014 9:18 AM


I constantly spent my half an hour to read this webpage's posts everyday

along with a mug of coffee.
Posted by: Hislop - Thursday, March 6, 2014 10:18 PM


I have been browsing online more than 2 hours

today, yet I never found any interesting article like yours.

It's pretty worth enough for me. Personally,

if all site owners and bloggers made good content as you did, the internet will be

a lot more useful than ever before.
Posted by: Hanger - Sunday, March 9, 2014 10:44 PM


Yesterday, while I was at work, my cousin stole my apple ipad and

tested to see if it can survive a thirty foot drop, just so she can be

a youtube sensation. My iPad is now broken and she has 83 views.

I know this is totally off topic but I had to

share iit with someone!
Posted by: Corley - Monday, March 10, 2014 1:04 PM


It's really a great and useful piece of info. I'm glad that

you simply shared this helpful information with us.

Please keep us up to date like this. Thanks for sharing.
Posted by: Malin - Monday, March 10, 2014 11:08 PM


Woah! I'm really loving the template/theme

of this blog. It's simple, yet effective. A lot of times

it's very difficult to geet that "perfect balance" between

superb usability and visual appearance. I must say you've

done a superb job with this. In addition, the blog loads extremely fast

for me on Safari. Exceptional Blog!
Posted by: Harbison - Wednesday, March 12, 2014 10:21 AM


I have been browsing online more than three hours lately, yet I never discovered any attention-grabbing article like yours.

It's beautiful price enough for me. In my view, if all site

owners and bloggers made just right content as you did, the net shall be much mre useful than ever before.
Posted by: Middleton - Wednesday, March 12, 2014 2:56 PM


I will right away grasp your rss feed as I can't in

finding your e-mail subscription hyperlink or newsletter

service. Do you have any? Kindly allow me know so that I could subscribe.

Thanks.
Posted by: Fincham - Sunday, March 16, 2014 3:38 PM


You need to take part in a contest for one of the finest blogs on the internet.

I most certainly will highly recommend this blog!
Posted by: Bickersteth - Sunday, March 16, 2014 8:56 PM


reverse phone lookup I��ve been exploring for a bit for any high-quality articles or weblog posts in this sort of house .

Exploring in Yahoo I eventually stumbled upon this web site.

Studying this info So i am satisfied to convey that I have a very just right uncanny feeling I found out just what I needed.

I so much unquestionably will make sure to don��t put out of your mind this web

site and give it a glance on a relentless basis. reverse phone
Posted by: Belair - Sunday, March 16, 2014 9:40 PM


Howdy, i read your blog occasionally and i own a similar one and i

was just curious if you get a lot of spam feedback? If so how

do you stop it, any plugin or anything you can suggest?

I get so much lately it's driving me insane so any help is very much appreciated.
Posted by: Nixon - Monday, March 17, 2014 1:50 AM


Hi there just wanted to give you a quick heads up.

The words in your content seem to be running off the screen

in Firefox. I'm not sure if this is a formatting issue or something to do with web browser compatibility but

I figured I'd post to let you know. The design and stle look great though!

Hope you get the problem solved soon. Many thanks
Posted by: Sowers - Monday, March 17, 2014 4:00 PM


Greetings! Very useful advice in this particular post!

It is the little changes which will mqke the biggest changes.

Many thanks for sharing!
Posted by: Sroka - Monday, March 17, 2014 5:27 PM


This iis a topic which is close to my heart...

Best wishes! Exactly wheree aare your contaht details though?
Posted by: Brett - Monday, March 17, 2014 6:52 PM


reverse phone lookup After study some of the blog posts on your own site now,

we really like your way of blogging. I bookmarked it to my bookmark internet

website list and are checking back soon. Pls consider

my web-site likewise and make me aware in the

event you agree. reverse phone
Posted by: Baehr - Monday, March 17, 2014 6:59 PM


reverse phone lookup What i do not realize is in reality how you_re now

not really much more smartly-favored than you might be right now.

You_re so intelligent. You understand therefore considerably on

the subject of this matter, produced me for my part believe it from numerous various angles.

Its like men and women don_t seem to be fascinated except

it_s one thing to do with Lady gaga! Your individual stuffs excellent.

At all times maintain it up!| reverse phone lookup
Posted by: Longstreet - Tuesday, March 18, 2014 12:38 AM


I like what you guys are up too. This type of clever work and exposure!

Keep up the wonderful works guys I've added you guys to my blogroll.
Posted by: Seiffert - Tuesday, March 18, 2014 2:39 AM


Paragraph writing is also a excitement, if you be acquainted

with then you can write if not it is complex to write.
Posted by: Best - Tuesday, March 18, 2014 10:59 AM


I am really loving tthe theme/design of your website. Do you ever run into any browaer compatibility issues?

A couple of my blog audience have complained about my blog not operaging correctly in Explorer but

looks great iin Firefox. Do you have any advice to help fix this issue?
Posted by: Belcher - Tuesday, March 18, 2014 8:23 PM


Wow, this post is fastidious, my sister is analyzing these things, therefore I

am going to convey her.
Posted by: Chun - Wednesday, March 19, 2014 3:17 PM


Hi Dear, are you genuinely visiting this site daily,

if so then you will without doubt take pleasant experience.
Posted by: Short - Wednesday, March 19, 2014 11:12 PM


I could not refrain from commenting. Very well written!
Posted by: Cusack - Thursday, March 20, 2014 4:50 AM


You need tto take part in a contest ffor oone of the

finest websites on the net. I will highly recommend thiss blog!
Posted by: Ledoux - Thursday, March 20, 2014 6:31 AM


Way cool! Some very valid points! I appreciate you writing this write-up and also the rest off

the site is also really good.
Posted by: Dumaresq - Friday, March 21, 2014 6:40 AM


Hello there, I discovered your web site by the use of Google whilst

looking for a similar topic, your web site came up, it seems to be good.

I've bookmarked it in my google bookmarks.

Hello there, simply changed into alert to your weblog through Google, and

found that it's truly informative. I'm gonna be careful for

brussels. I will appreciate for those who proceed this

in future. Numerous other people will be benefited from your writing.

Cheers!
Posted by: Darrington - Friday, March 21, 2014 8:48 AM


gillette venus samples
Posted by: Hawes - Saturday, March 22, 2014 5:36 PM


Hola! I've been reading your weblog for a long time now and finally got the bravery to go ahead

and give you a shout out from Huffman Tx! Justt wanted to mention keep up the great work!
Posted by: Rummel - Sunday, March 23, 2014 5:15 PM


garcinia cambogia reviews Adirondack recliners? any anyone wear caution in which your pet plus i actually returned9,

. This may fundamentally boosted as a result of the fresh accessory associated with training video, At wholesale prices The actual Northern Facial area Back

packs low cost upper encounter outdoor jackets.

garcinia cambogia reviews
Posted by: McCorkindale - Sunday, March 23, 2014 10:00 PM


I write a leave a response each time I especially enjoy a post on a

site or I have something to add to the discussion. Usually it is a result of the sincerness displayed in the

post I browsed. And on this article blo topic.

I was actually excited enough to post a comment ;-) I actually do have

a few questions for you if you do not mind. Is it only me or do

a few of the comments come across like they are left by brain dead individuals?

:-P And, if you are writing on other online social sites, I'd like too follow you.

Would you make a list the complete urls of

your shared pages like your twitter feed, Facebook page or linkedin profile?
Posted by: McCarten - Sunday, March 23, 2014 10:23 PM


natural garcinia cambogia reviews I have observed that of all different types of insurance, medical

care insurance is the most questionable because

of the conflict between the insurance plan company_s obligation to remain afloat

and the client_s need to have insurance cover. Insurance companies_ income

on health plans are very low, hence some businesses struggle to earn profits.

Thanks for the tips you talk about through this site. miracle garcinia cambogia reviews
Posted by: Welsby - Wednesday, March 26, 2014 5:59 AM


reverse phone lookup free results Some genuinely superb articles on this website, appreciate

it for contribution. _Be absolutely determined to

enjoy what you do._ by Sarah Knowles Bolton.

reverse phone lookup yellow pages
Posted by: Cartwright - Thursday, March 27, 2014 7:33 PM


reverse lookup 882864 330370Extremely man or woman

speeches require to seat giving observe into couples. Brand new sound system just before unnecessary individuals ought to always be mindful of usually senior general rule from public speaking, which is to be

the mini. greatest man speaches 422576 reverse lookup
Posted by: Leroy - Friday, March 28, 2014 7:25 PM


reverse phone number lookup free _This hammer

is eight Ling absolute being hammer, get from __._That inborn superior has intention to of show

own eight Ling absolute being hammer, what then Sun Wukong listens to also not listen to, see also not see,

pure of consider as it transparent thing. reverse phone lookup
Posted by: Colwell - Monday, March 31, 2014 2:07 AM


garcinia cambogia reviews Fertility can decrease with age because of poor quality of sperm production.

garcinia cambogia reviews
Posted by: Nicolle - Sunday, May 4, 2014 4:33 AM


I saw firsthand who was making money and who wasn't, what worked and what didn't,

what people wanted that wasn't available and what was to easy to find but wasn't wanted.

Easements are created when another property owner (or interested party) requires access

to property that may only be accessed from

the primary owner's property. Crushed and made into

soft, tumbled stone, glass becomes a practical and visually

appealing second-hand product.
Posted by: Roth - Saturday, July 5, 2014 1:11 AM


I will right away take hold of your rss feed as I can not to find your

email subscription link or newsletter service. Do you have any?

Please allow me recognise so that I may subscribe.

Thanks.
Posted by: Schlemmer - Saturday, August 9, 2014 11:30 AM


Thanks for sharing your thoughts about Fast loans.

Regards
Posted by: Pitre - Friday, September 19, 2014 11:38 AM


Use acceptable synchronous language same "assemblage" and "TV show accumulation organized for...," as they address, which could

get it on right to redeemable online codes for subject field online retailers you already own. mould divergent necklaces

of several factors. When hit take a shit reliable that the vendor foremost.

You should be to a greater extent lettered astir Cheap NFL Jerseys Cheap NFL Jerseys Authentic NFL Jerseys Wholesale Jerseys China Wholesale NFL Jerseys USA Wholesale NFL Jerseys China your sector on the game equipment are bang-up examine railway

locomotive assessment. A near manner tip is to discovery out if on that

point are any coupons offered. There are many holding to ensure your assemblage

equivalent a pro and hear cracking deals, ownership your lineament and combination up for a
Posted by: Fogle - Thursday, October 2, 2014 11:27 PM


 









WPL
PUBLISHING CO, INC.
WPL Publishing - 5750 Bou Avenue #1712 - Rockville, MD 20852

Phone: (301)983-0443  -  Fax: (301)983-4367

All Content and Design Copyright © 2026 WPL Publishing
About Us

Contact Us

Privacy Policy

My Account