ConstructionPro Week, Volume: 2 - Issue: 45 - 11/08/2013

Do Overreaching Claims Give the Process a Bad Name?

By Bruce Jervis

 

There are many legitimate reasons for contractors to submit claims for increased compensation. Construction contracts, which essentially allocate risks and responsibilities between project owners and constructors, spell out the circumstances under which the contractor may be entitled to additional time or money. This is why aspersions such as “claim monger” are offensive to contractors.

 

Sometimes, however, contractors overreach. These lapses in judgment are harmful to the image of the industry and give the entire claim process a bad reputation. An example is found in a recent federal court case in Wisconsin.

 

A gas pipeline was being installed in an open cut trench in an area of high groundwater. The bid schedule called for off-site disposal, at a permitted facility, of an estimated 15,000 gallons of contaminated groundwater. The contractor bid $1.50 per gallon. The contractor pumped almost 5 million gallons of water from the trench, but the level of contamination was so low that all of the water could be pumped into an existing on-site manhole that led to a municipal treatment facility. The contractor claimed unit-price payment for “disposal” of all that water.

 

Have you seen claims that don’t pass the straight-face test? These would include claims that are grossly exaggerated or claims that are simply not supported by the facts or the contract documents. Do claims such as this harm the reputation of the claim process and make it harder for ethical contractors to recover on legitimate claims? I welcome your input.

 

COMMENTS

All construction projects have claims. As in the case above, it involved indefinite quantities. I can't say it harms the reputation of the claims process, that is what it is for. We usually see excessive claims when there is a big difference between the low and next low bid prices. Contractors want to make that money up and they use the claims process to do it. I can tell you that it definitely harms the reputations of both the contractor and the engineer involved. I can also tell you that it is a definite strategy with certain contractors to allow them to under-bid their competition and it adversely effects their reputations.
Posted by: Mark Lentz - Friday, November 8, 2013 11:01 AM


Claims are a neccessary part of the process to allow contractors to voice a position that they feel that they have been wronged or recover costs for items not included in project scope. I have seen the gammit run from excessive as aformentioned to reasonable request for items not included in the scope of the work. In the above the claim could have been avoided if the specification indicated a level of contamination and gave a clear definition. At the end of the day claims reflect the quality of the documents, the due dilligence of the contractor to follow those documents. If a contractor sees during the bidding process holes in the project scope that he can turn than into an advantage during the project, that is unfortunate but a reality of our bussiness climate today. I only expect a contractor to provide what is indicated in the project scope an no more, if additional work is determined he should be fairly compensated and not allowed to abuse the process to gouge the project.
Posted by: Chris A Addington, FARA, AIA - Friday, November 8, 2013 11:22 AM


On its face, the contractor apparently bid a unit price for the disposal contaminated groundwater and was neither paid that price nor able to negotiate an equitable adjustment for the changed condition (i.e., lower level of contamination). Hence, this claim is straight-forward (i.e., "Pay me what I bid for off-site disposal at a permitted municipal treatment facility"). All construction claims rest upon three essential proofs (i.e., proof of liability, proof of causation, and proof of damages). Proof of liability is a question of the contract and the law. Proof of causation and damages are questions of fact. What can be more is that ambiguities in a contract are construed against the drafter, the law can have unintended consequences, and the facts can prove entitlement to what can appear to a respondent as unfair or unethical.
Posted by: Richard Bull - Friday, November 8, 2013 11:28 AM


The aforementioned points notwithstanding, the author fails to point out that one of the most basic legal tests of even the existence of a contract is whether the parties had a 'meeting of the minds'. No such 'meeting', no contract. Construction Management courses at ABET accredited universities include curriculum that describe changes in excess of 20% as "cardinal". Since when is it reasonable to assume a 33,233.3% increase in contract price (and volume) reflects such an agreement? Just plowing on and demanding the bill be paid, without making a substantial effort to alert the owner and seek resolution on such an extravagent expenditure, reflects an effort on the contractor's part to not have that 'meeting of the minds', and just ring the register at the expense of the owner. Only contracts, explicit or implied, have liability. I see no explicit or implied contract for such an extensive difference, hence no liability. Would you return your car to the dealer because your Impala doesn't fly? Would you take your TV to your car mechanic because the sound is awful? Some differences are glaring, others not as much, but a 33,233.3% difference? Really? That's not a contract.
Posted by: Tony Keller - Wednesday, November 13, 2013 12:04 PM


My brother recommended I might like this web site.

He was totally right. This put up actually made my day.

You cann't consider just how much time I had spent for this info!

Thank you!
Posted by: Correia - Saturday, November 16, 2013 8:09 AM


I'm not sure where you're getting your information, but great topic.

I needs to spend some time learning much more or understanding more.

Thanks for magnificent information I was looking for

this info for my mission.
Posted by: Foulds - Tuesday, January 21, 2014 12:01 PM


top auto insurance companies - cheap car insurance online - texas car

insurance
Posted by: McCollister - Tuesday, January 21, 2014 3:31 PM


WOW just what I was looking for. Came here by searching

for click through the next page
Posted by: Hartford - Monday, January 27, 2014 2:02 PM


I always spent my half an hour to read this weblog's posts every day

along with a mug of coffee.
Posted by: Henson - Friday, January 31, 2014 12:47 PM


Once they have got decided for the amount in the loan which obtaining a loan is their finest option they ought to shop around to the best loan not Fake when you happen to be considering buying your own home, there are several things to take into

consideration.
Posted by: Snider - Thursday, February 13, 2014 9:44 PM


Looking for a pay day loan can be tiring - when there's so many on the market, just how

do you ultimately choose my website for consumers with negative credit rating or

for all those who do not have secureness, a payday loan is probably the best

choice for you.
Posted by: Boshears - Wednesday, February 19, 2014 1:55 AM


Aloe Vera and garlic are used today for their varied skin care and nutritional values.

All of these facial wart removal tactics and techniques to work, but they usually wound marks or

scars. In any case, the treatment of warts is necessary regardless of whether this is a

cosmetic or much more dangerous problem.
Posted by: Lake - Friday, February 28, 2014 9:50 AM


When some one searches for his necessary thing, thus he/she wishes to

be available that in detail, therefore that thing is maintained over here.
Posted by: Deason - Monday, March 3, 2014 2:32 AM


I really like your blog.. very nice colors & theme.

Did you create this website yourself or did you hire someone to do

it for you? Plz respond as I'm looking to design my own blog and would like

to know where u got this from. appreciate it
Posted by: Rowntree - Saturday, March 8, 2014 11:32 AM


Hey there! I've been reading your site for a while now and finally got the bravery to go ahead and give you a shout

out from New Caney Tx! Just wanted to tell you

keep up the excellent job!
Posted by: Sanchez - Saturday, March 8, 2014 6:43 PM


Hi there, i read your blog from time to time and i own a similar one and i

was just wondering if you get a lot of spam responses?

If so how do you reduce it, any plugin or anything you can

advise? I get so much lately it's driving me crazy

so any help is very much appreciated.
Posted by: Birdsong - Sunday, March 9, 2014 4:02 PM


Right here is the perfect site for anybody who wishes to understand this topic.

You know so much its almost tough to argue with you (not that

I actually will need to_HaHa). You certainly put a brand new spin on

a subject which has been written about for

ages. Excellent stuff, just wonderful!
Posted by: Berry - Tuesday, March 11, 2014 2:27 AM


New players too will find the game easy to follow as the menus and sub-menus follow a logical

order, so game options are easy to find. It is commonly

the only method that gamers of the game can get their hands

on the extremely finest players. Article first published as Play - Station 4 Review:

'FIFA 14' on Blogcritics.
Posted by: Crawford - Tuesday, March 11, 2014 7:07 PM


The key message here is that the availability of task-involving cues in sports that are naturally ego

involving allows the athlete to develop a more task-involved approach to competition.

England's bid team has promised FIFA "the most spectacular World Cup in history" ahead of the vote.

The previous week has witnessed the annual Wreck

Beach Bare Buns Run, the PGA Championship, the New York Red Bulls, the FIS Summer Grand Prix,

the World Badminton Championships, and the friendly football match between Scotland and Denmark and so on.
Posted by: Wile - Wednesday, March 12, 2014 6:54 PM


Truly no matter if someone doesn't know then its up to other visitors that they

will assist, so here it takes place.
Posted by: Espinal - Saturday, March 15, 2014 2:04 PM


Hello this is kinda of off topic but I was wanting to know

if blogs use WYSIWYG editors or if you have to manually

code with HTML. I'm starting a blog soon but have no coding knowledge so I wanted to

get advice from someone with experience. Any help would be enormously

appreciated!
Posted by: Zarate - Saturday, March 15, 2014 10:07 PM


Its like you learn my mind! You seem to know so much approximately this, such

as you wrote the guide in it or something. I feel that you just could

do with a few percent to drive the message house a

little bit, but other than that, this is

wonderful blog. A fantastic read. I will definitely be back.
Posted by: Swigert - Sunday, March 16, 2014 6:13 AM


Hello there! Quick question that's entirely off topic.

Do you know how to make your site mobile friendly? My blog

looks weird when viewing from my iphone4. I'm trying to find a theme or plugin that might be able to correct this issue.

If you have any suggestions, please share. Appreciate

it!
Posted by: Ferrer - Tuesday, March 18, 2014 8:03 AM


Hi! I've been reading your blog for some time

now and finally got the bravery to go ahead and give you a shout out

from Lubbock Tx! Just wanted to tell you keep up the excellent work!
Posted by: Thomason - Tuesday, March 18, 2014 11:47 PM


Thanks for sharing your thoughts on sbobet. Regards
Posted by: Cobbett - Thursday, March 20, 2014 6:53 AM


Superb post but I was wondering if you could write a litte

more on this subject? I'd be very grateful if you could elaborate a little bit more.

Thanks!
Posted by: Lapointe - Thursday, March 20, 2014 7:26 AM


Excellent post. I will be experiencing a few of these issues as

well..
Posted by: Chapin - Thursday, March 20, 2014 3:12 PM


I'm not certain the place you are getting your information,

but great topic. I must spend a while studying much more or figuring out more.

Thanks for excellent info I used to be searching

for this information for my mission.
Posted by: Amos - Friday, March 21, 2014 9:09 PM


The demand ffor escorts in Harrow Hill iss on the upswing.

Rihanna was dressed in a stunning Azedine Alaia robe that

she combined with Neil Lane jewelry. Have you been the one to initiate most of thee calls?

http://www.datalogger.co.kr/xe/?document_srl=2461814
Posted by: Burkholder - Saturday, March 22, 2014 4:19 PM


Thanks for the good writeup. It in truth was once a leisure account it.

Look advanced to far added agreeable from you! By the way, how can we keep in touch?
Posted by: Petersen - Sunday, March 23, 2014 11:43 AM


Hi I am so excited I found your weblog, I really found you by error, while I was looking on Aol for something else, Anyhow I am here now and would

just like to say thanks a lot for a tremendous post and a all round entertaining

blog (I also love the theme/design), I don_t have time to read it all at the moment but I have saved it and

also added your RSS feeds, so when I have time I will be back to read a great deal more, Please do keep up the

awesome jo.
Posted by: Samson - Sunday, March 23, 2014 11:46 AM


Google seem to be so proud that they can now find duplicates to a paragraph.

And Credits has gotten a big boost with this week's launch of

Facebook Deals. Sage Agasthiya pioneered the traditional Indian

Medicine and wrote more than 96 books.
Posted by: Pennington - Sunday, March 23, 2014 9:25 PM


Blind Dating: 1 of the most fascinating video games!You will make a reduction on

the shares but this will be neutralisd by the higher cwll top quality you received.

They are really there to sedve and to make sure you

you. https://energy.korea.com/activity-2/p/88671/
Posted by: Colunga - Monday, March 24, 2014 10:09 AM


Check with your teleconferencing assistance supplier on any complex aspects

that you are unclear. Its reputation off being the Entertainment Money of

the World is all worth it. http://Yeosamo.net/xe/?document_srl=107534
Posted by: Belz - Tuesday, March 25, 2014 8:39 AM


Everything posted was very reasonable. But, what about

this? suppose you addrd a little information? I am not saying your content isn't solid., but whqt if you added a title that maes people desire more?

I mean blog topic is a little plain. Yoou hould glance at Yahoo's

home page and note how they create news headlines to grab people interested.

You might addd a related video or a related picture orr two

too geet readers excited about what you've got too say.

Just my opinion, it could bring yiur posts a little livelier.
Posted by: Cason - Tuesday, March 25, 2014 12:13 PM


dialogue on the topic of this article here at this website, I have

read all that, so now me also commenting at this place.|

I am sure this piece of writing has touched all the internet users, its really really good post on building

up new blog.|

Wow, this post is nice, my sister is analyzing these things, therefore I am going to tell her.|

Saved as a favorite, I love your web site!|

Way cool! Some very valid points! I appreciate you

coach outlet store online
Posted by: Najera - Wednesday, March 26, 2014 8:07 AM


Whhen you see a reoccurring theme here. So you can always

add more to it or take away from thee relationship.

Quite a number of people who will i get my boyfriend back are having the right relationship for

you both. This important professional relationship in psychology can help a friend who,

when he basically said it was me?
Posted by: Kiddle - Wednesday, March 26, 2014 9:09 AM


This desire to cfeate and to role-play and to have freedom of choice was

a large part of what my wife and I both loved about

the MUD community. It worked exponentially' if we talk about the present

day situation gaming world has grown big. The bigger it is, the quicker your own gaming laptop will probably be and also

the more you'll get to take pleasure from your games.
Posted by: Lawrence - Wednesday, March 26, 2014 9:57 AM


Everyone loves what you guys tend to be up too.

This type of clever work and reporting! Keep up the

good works guys I've you guys to my personal blogroll.

official michael kors outlet
Posted by: Barreiro - Thursday, March 27, 2014 2:45 AM


hi!,I love your writing so a lot! proportion we keep in touch

extra about your article on AOL? I need a specialist in this

space to solve my problem. May be that is you! Looking ahead to look you.
Posted by: Collette - Saturday, March 29, 2014 2:33 AM


Does your site have a contact page? I'm having a tough time

locating it but, I'd like to shoot you an email.

I've got some suggestions for your blog you might be interested in hearing.

Either way, great blog and I look forward to seeing it develop over time.
Posted by: Batson - Saturday, March 29, 2014 8:34 AM


Culture today haas abused that priviledge and sex has lost it's which means.

Just envision srnding a letterr in January so that you can bee able to satisfy your lovwr in April.

http://support.camzap.com/entries/27808460-Protected-Under-Escort-Service-Prices-NJ
Posted by: Hardman - Monday, March 31, 2014 7:03 AM


Thanks for another magnificent post. Where else may

anyone get that type of information in such a perfect manner of

writing? I've a presentation subsequent week, and I am at the look for such info.
Posted by: Wisniewski - Monday, March 31, 2014 3:52 PM


This paragraph presents clear idea in favor of the new viewers of blogging, that actually how to do running a blog.
Posted by: McCloughry - Thursday, April 3, 2014 12:14 AM


Magnificent beat ! I would like to apprentice even as you amend

your site, how could i subscribe for a blog web site?

The account helped me a applicable deal. I have been tiny bit familiar of

this your broadcast provided bright transparent idea
Posted by: Teresa - Wednesday, April 9, 2014 10:27 AM


I desired to say a quick thank you for this handy info!
Posted by: Elkin - Thursday, April 10, 2014 11:58 PM


My partner and I absolutely love your blog and find most of your

post's to be exactly I'm looking for. Would you offer guest writers to write content available

for you? I wouldn't mind composing a post or elaborating on most of the subjects you write about here.

Again, awesome web log!
Posted by: Follansbee - Wednesday, June 11, 2014 12:37 AM


Very soon this site will be famous amid all blog visitors,

due to it's pleasant articles
Posted by: Bogner - Wednesday, June 11, 2014 1:04 AM


Hi there, i read your blog from time to time and i own a similar one

and i was just wondering if you get a lot of spam

responses? If so how do you stop it, any plugin or anything

you can advise? I get so much lately it's driving me crazy so any support

is very much appreciated.
Posted by: Meudell - Wednesday, June 11, 2014 3:19 AM


What i don't realize is if truth be told how you are no longer actually a lot more smartly-liked than you might be right now.

You are so intelligent. You know therefore significantly when it comes

to this subject, produced me in my view imagine it from so

many varied angles. Its like women and men are not interested except it's one thing to accomplish with Woman gaga!

Your individual stuffs excellent. At all times deal with it up!
Posted by: Windeyer - Wednesday, June 11, 2014 10:14 AM


Why viewers still make use of to read news papers when in this technological world all is accessible on web?
Posted by: Butler - Wednesday, June 11, 2014 11:04 AM


This is a really good tip especially to those new to the blogosphere.

Short but very precise information_ Thank you for sharing this one.

A must read post!
Posted by: Delapena - Wednesday, June 11, 2014 12:52 PM


After going over a few of the blog articles on your

web page, I honestly like your way of writing a blog.

I book-marked it to my bookmark website list and will

be checking back soon. Take a look at my web site as well and let

me know what you think.
Posted by: Bussau - Monday, December 7, 2015 3:45 PM


Superb blog! Do you have any hints for aspiring writers?

I'm planning to start my own site soon but I'm a little lost on everything.

Would you suggest starting with a free platform like Wordpress or go for a paid option? There are so many options out there that I'm totally overwhelmed ..

Any tips? Appreciate it!
Posted by: Helbig - Friday, December 25, 2015 10:35 AM


It's going to be finish of mine day, except before finish I am reading this

fantastic post to improve my knowledge.
Posted by: Pinschof - Tuesday, December 29, 2015 1:35 AM


A fascinating discussion is definitely worth comment.

I do believe that you need to write more about this subject, it might not be

a taboo matter but generally people do not talk about

such subjects. To the next! Many thanks!!
Posted by: Gertz - Tuesday, December 29, 2015 3:34 AM


obviously like your web site however you have to test the spelling on several of your posts.

Many of them are rife with spelling problems and I find it very troublesome to tell the reality

however I will definitely come again again.
Posted by: Teeple - Tuesday, December 29, 2015 3:54 AM


Today, while I was at work, my cousin stole my iPad and tested to see if it can survive a 30 foot drop, just

so she can be a youtube sensation. My apple ipad is now broken and she has 83 views.

I know this is completely off topic but I

had to share it with someone!
Posted by: Kingsley - Wednesday, January 6, 2016 9:13 AM


We are a bunch of volunteers and starting a brand new scheme in our community.

Your site offered us with useful info to work on.

You've done a formidable process and our whole group will be thankful to

you.
Posted by: Stott - Monday, January 11, 2016 12:13 PM


hello there and thank you for your info – I have certainly picked up anything new from right here.

I did however expertise several technical issues

using this site, as I experienced to reload the site lots of times previous to

I could get it to load correctly. I had been wondering if

your web hosting is OK? Not that I'm complaining, but slow loading instances

times will sometimes affect your placement in google and can damage your

high-quality score if advertising and marketing with Adwords.

Well I am adding this RSS to my email and could look out for a lot more of your respective intriguing content.

Ensure that you update this again very soon.
Posted by: Nicholson - Tuesday, January 12, 2016 11:15 PM


Do you mind if I quote a couple of your articles as long

as I provide credit and sources back to your webpage?

My blog is in the exact same area of interest as yours

and my visitors would genuinely benefit from a lot of the information you

provide here. Please let me know if this alright with you. Thanks a lot!
Posted by: Agaundo - Wednesday, January 13, 2016 7:27 PM


That is very interesting, You are an excessively professional blogger.

I've joined your rss feed and stay up for

seeking extra of your magnificent post. Also, I've shared your

site in my social networks
Posted by: Ding - Thursday, January 14, 2016 4:34 AM


bookmarked!!, I really like your blog!
Posted by: Clarey - Thursday, January 14, 2016 4:56 AM


This is a topic that's near to my heart... Many thanks!

Exactly where are your contact details though?
Posted by: Rivers - Thursday, January 14, 2016 10:22 AM


I all the time used to study article in news papers but now as I

am a user of web thus from now I am using net

for content, thanks to web.
Posted by: Turner - Friday, January 15, 2016 6:11 AM


This is a very good tip especially to those fresh to the blogosphere.

Short but very accurate info… Appreciate your sharing this one.

A must read article!
Posted by: Koehler - Monday, January 18, 2016 5:46 AM


Hello Dear, are you in fact visiting this site on a

regular basis, if so after that you will without doubt get pleasant experience.
Posted by: Batman - Monday, January 18, 2016 7:34 AM


That is a really good tip especially to those fresh to the

blogosphere. Short but very precise information… Thank

you for sharing this one. A must read post!
Posted by: Mileham - Monday, January 18, 2016 5:35 PM


Magnificent web site. A lot of helpful information here. I am sending it to a few friends ans additionally sharing in delicious.

And of course, thanks for your effort!
Posted by: Bingaman - Tuesday, January 19, 2016 2:13 PM


I am sure this piece of writing has touched all the

internet visitors, its really really fastidious piece of writing on building up new

web site.
Posted by: Silvestri - Wednesday, January 20, 2016 6:21 AM


I feel this is one of the so much vital info for me. And i am happy studying your article.

But wanna observation on some basic things, The

site taste is perfect, the articles is really great : D.

Excellent task, cheers
Posted by: Mares - Thursday, January 21, 2016 1:40 PM


Hey there excellent blog! Does running a blog similar to this require a massive amount work?

I've absolutely no knowledge of computer programming however I was hoping to start my own blog soon. Anyway, if you have any

recommendations or tips for new blog owners please share. I understand this is off topic

nevertheless I simply needed to ask. Thanks a lot!
Posted by: Birmingham - Friday, January 22, 2016 2:08 AM


Quality posts is the important to attract the visitors

to pay a visit the site, that's what this web page is providing.
Posted by: McVey - Sunday, January 24, 2016 7:46 PM


Thanks for the good writeup. It in fact was once a enjoyment account it.

Glance advanced to more introduced agreeable from you!

However, how could we keep up a correspondence?
Posted by: Free - Sunday, January 24, 2016 10:20 PM


I loved as much as you will receive carried out right here.

The sketch is attractive, your authored subject matter stylish.

nonetheless, you command get got an shakiness over that you

wish be delivering the following. unwell unquestionably come further formerly again since exactly the same nearly a lot

often inside case you shield this increase.
Posted by: Crotty - Monday, January 25, 2016 2:28 AM


I think what you composed was very reasonable. However, think on this,

suppose you were to create a awesome headline? I

mean, I don't want to tell you how to run your blog, however what if you added a post title to maybe get

a person's attention? I mean blog topic is kinda boring.

You should glance at Yahoo's home page and see how they write post titles

to get viewers interested. You might add a related video or

a pic or two to get readers interested about what

you've got to say. Just my opinion, it might bring your posts a little bit more interesting.
Posted by: Shackleton - Friday, January 29, 2016 4:03 PM


Hi, I do believe this is a great blog. I stumbledupon it

;) I am going to return once again since i have bookmarked it.

Money and freedom is the best way to change, may you be rich and continue to help

other people.
Posted by: Law - Tuesday, February 2, 2016 7:15 AM


Pretty component to content. I just stumbled upon your blog and in accession capital to assert that I get actually enjoyed

account your weblog posts. Anyway I will be subscribing for your augment or even I achievement you

get admission to constantly fast.
Posted by: Harriet - Wednesday, February 3, 2016 6:32 AM


I don't even know how I ended up right here, however I assumed this post

used to be great. I do not understand who you might be but certainly you're going to a famous blogger if you are

not already. Cheers!
Posted by: Whitaker - Sunday, February 7, 2016 3:24 PM


Thanks to my father who told me about this blog, this webpage is actually remarkable.
Posted by: Fite - Sunday, February 7, 2016 7:11 PM


If you would like to improve your know-how simply keep visiting this website and be updated with the newest news posted here.
Posted by: Woodbury - Sunday, February 7, 2016 10:24 PM


Hey there! This is my first visit to your blog!

We are a collection of volunteers and starting a new

project in a community in the same niche. Your blog

provided us beneficial information to work on.

You have done a wonderful job!
Posted by: Sepulveda - Monday, February 8, 2016 2:26 AM


Does your site have a contact page? I'm having trouble locating it but,

I'd like to send you an email. I've got some creative ideas for your

blog you might be interested in hearing. Either way, great blog

and I look forward to seeing it expand over time.
Posted by: Mckenney - Monday, February 8, 2016 4:22 AM


This design is wicked! You definitely know how to keep

a reader entertained. Between your wit and your videos,

I was almost moved to start my own blog (well, almost...HaHa!) Excellent job.

I really enjoyed what you had to say, and more than that, how

you presented it. Too cool!
Posted by: Sauer - Monday, February 8, 2016 5:12 AM


fantastic put up, very informative. I'm wondering why the opposite specialists of this sector don't understand this.

You must proceed your writing. I am confident, you've a great readers' base already!
Posted by: Brient - Monday, February 8, 2016 7:54 AM


These are truly enormous ideas in concerning blogging.

You have touched some fastidious points here. Any way keep up

wrinting.
Posted by: Barger - Monday, February 8, 2016 11:13 PM


whoah this weblog is excellent i like studying your posts.

Keep up the good work! You recognize, many individuals are searching round for this

information, you could help them greatly.
Posted by: Cilley - Tuesday, February 9, 2016 6:27 AM


Sweet blog! I found it while surfing around on Yahoo News. Do you have any tips on how to get listed in Yahoo

News? I've been trying for a while but I never seem to get

there! Cheers
Posted by: Steven - Tuesday, February 9, 2016 7:17 AM


Generally I don't learn post on blogs, but I wish to say that this write-up very forced me to try and do so!

Your writing taste has been surprised me. Thank you,

quite great post.
Posted by: Chestnut - Tuesday, February 9, 2016 3:38 PM


Hmm is anyone else having problems with the pictures on this blog loading?

I'm trying to determine if its a problem on my end or if it's the blog.

Any responses would be greatly appreciated.
Posted by: Reginald - Wednesday, February 10, 2016 10:35 PM


I just could not depart your web site prior to suggesting that I extremely enjoyed

the standard information a person supply in your guests?

Is gonna be again regularly to investigate cross-check new

posts
Posted by: Delossantos - Saturday, February 13, 2016 1:27 PM


Hello! I could have sworn I've visited this blog before but after looking at

some of the articles I realized it's new to me.

Regardless, I'm definitely pleased I discovered it and

I'll be book-marking it and checking back regularly!
Posted by: Wertheim - Sunday, February 14, 2016 12:39 PM


Hi there! I could have sworn I've visited this blog before but after browsing through some of the posts I realized it's new to me.

Anyways, I'm certainly happy I discovered it and I'll be book-marking it and

checking back often!
Posted by: Elam - Sunday, February 14, 2016 5:14 PM


Hello there, just became aware of your blog through Google, and found that it is truly informative.

I'm going to watch out for brussels. I'll appreciate if you continue this in future.

A lot of people will be benefited from your writing.

Cheers!
Posted by: Milford - Thursday, February 18, 2016 8:59 AM


Every weekend i used to pay a quick visit this site, because

i want enjoyment, as this this web site conations actually nice funny data too.
Posted by: Umbagai - Monday, February 22, 2016 9:58 AM


Undeniably believe that that you said. Your favorite justification seemed to be at the internet the simplest factor to consider of.

I say to you, I certainly get annoyed even as people think about

worries that they plainly don't realize about. You managed to

hit the nail upon the top and defined out the whole thing without having side effect ,

folks can take a signal. Will probably be again to

get more. Thank you
Posted by: Waldon - Friday, February 26, 2016 5:14 PM


Hello everyone, it's my first pay a quick visit at this web site,

and post is truly fruitful in support of me, keep up posting

such articles.
Posted by: Fulmore - Monday, March 7, 2016 2:10 PM


Definitely consider that which you said. Your favourite reason appeared to be at the net the easiest thing to take into account of.

I say to you, I certainly get annoyed at the same time as folks consider issues that they plainly don't understand about.

You controlled to hit the nail upon the highest and also outlined out the entire thing without having side effect

, people can take a signal. Will likely be again to get more.

Thank you
Posted by: Heffner - Tuesday, March 15, 2016 1:04 AM


Woah! I'm really loving the template/theme of this site.

It's simple, yet effective. A lot of times it's tough to get that "perfect balance" between user friendliness and visual appearance.

I must say that you've done a very good job with this. Additionally, the blog loads very

fast for me on Internet explorer. Superb Blog!
Posted by: Whitney - Saturday, March 19, 2016 6:46 AM


First off I would like to say wonderful blog! I had a quick

question that I'd like to ask if you do not

mind. I was curious to find out how you center yourself and clear your thoughts before writing.

I've had a tough time clearing my thoughts in getting my ideas out there.

I do enjoy writing however it just seems like the first 10 to 15 minutes are generally wasted

just trying to figure out how to begin. Any recommendations

or hints? Appreciate it!
Posted by: Waterhouse - Saturday, March 19, 2016 4:52 PM


My coder is trying to persuade me to move to .net from PHP.

I have always disliked the idea because of the

expenses. But he's tryiong none the less. I've been using Movable-type on a variety of websites for about

a year and am concerned about switching to another platform.

I have heard fantastic things about blogengine.net. Is there a way I can import all my wordpress content into it?

Any help would be really appreciated!
Posted by: Cudmore - Wednesday, March 23, 2016 7:43 AM


Its like you read my mind! You appear to know so much about this,

like you wrote the book in it or something. I think that you can do with some pics to drive the message home

a little bit, but other than that, this is great blog.

A fantastic read. I will certainly be back.
Posted by: Cascarret - Wednesday, March 23, 2016 8:38 AM


Thankfulness to my father who informed me about this blog,

this webpage is truly amazing.
Posted by: Turriff - Wednesday, March 23, 2016 5:59 PM


I’m not that much of a internet reader to be honest

but your blogs really nice, keep it up! I'll go ahead and bookmark your website to

come back in the future. All the best
Posted by: Rocher - Thursday, March 24, 2016 5:37 AM


I read this post fully concerning the resemblance of most up-to-date and preceding

technologies, it's amazing article.
Posted by: McFarlane - Thursday, March 24, 2016 8:02 AM


Why visitors still make use of to read news papers when in this technological globe the whole thing is

available on net?
Posted by: Wayne - Friday, March 25, 2016 4:23 AM


I feel this is among the most important info for me. And i am happy studying your article.

However should statement on few basic things, The web site style is wonderful,

the articles is in point of fact nice : D. Good process,

cheers
Posted by: Haag - Friday, March 25, 2016 5:22 AM


Hey there I am so grateful I found your website,

I really found you by mistake, while I was searching on Askjeeve for something else, Nonetheless I am here now and

would just like to say cheers for a marvelous post and a all round entertaining blog (I

also love the theme/design), I don’t have time to read through it all at the moment but I have

book-marked it and also added in your RSS feeds, so when I have time I will be back to read more, Please do keep up

the excellent b.
Posted by: Halligan - Friday, March 25, 2016 9:32 AM


It is actually a great and useful piece of information. I am satisfied that you

shared this useful info with us. Please stay us up to date like this.

Thanks for sharing.
Posted by: Vosburg - Sunday, March 27, 2016 3:13 AM


Howdy! I realize this is sort of off-topic but I needed to ask.

Does managing a well-established website such as yours require

a large amount of work? I am completely new to running a blog but I do

write in my journal daily. I'd like to start a blog so I can share my

own experience and views online. Please let me know if you have any kind of

recommendations or tips for new aspiring bloggers. Appreciate it!
Posted by: Durkin - Monday, March 28, 2016 6:06 AM


Great post! We are linking to this particularly great post on our website.

Keep up the great writing.
Posted by: Shelly - Monday, March 28, 2016 3:04 PM


What's up i am kavin, its my first time to commenting anyplace,

when i read this paragraph i thought i could also create

comment due to this brilliant paragraph.
Posted by: Odum - Wednesday, March 30, 2016 4:33 PM


What's up, just wanted to mention, I liked this blog post.

It was inspiring. Keep on posting!
Posted by: Baldessin - Thursday, March 31, 2016 5:34 AM


Hello to all, because I am genuinely eager of reading this webpage's post to

be updated on a regular basis. It consists of good material.
Posted by: Allred - Friday, April 1, 2016 1:33 AM


great submit, very informative. I wonder why the opposite experts of this sector don't understand this.

You must proceed your writing. I'm confident, you've a great

readers' base already!
Posted by: Amey - Friday, April 1, 2016 6:46 AM


Your style is really unique compared to other folks I have

read stuff from. Many thanks for posting when you've got the opportunity, Guess I'll just

book mark this site.
Posted by: Auld - Friday, April 1, 2016 9:37 PM


I got this web site from my friend who informed me concerning this website and now

this time I am visiting this site and reading very informative content at this place.
Posted by: Rhea - Saturday, April 2, 2016 12:49 PM


If you want to improve your knowledge simply keep visiting this site and be updated with the most up-to-date gossip posted here.
Posted by: Marconi - Saturday, April 2, 2016 1:07 PM


I know this site presents quality based articles and extra stuff, is there any other web page which gives these kinds of data in quality?
Posted by: Umberger - Saturday, April 2, 2016 5:20 PM


Thank you for the good writeup. It in reality was a amusement account it.

Look complex to far delivered agreeable from you!

By the way, how can we keep up a correspondence?
Posted by: Connor - Sunday, April 3, 2016 12:59 AM


Howdy! This is kind of off topic but I need some advice from an established blog.

Is it very difficult to set up your own blog? I'm not very techincal but I can figure

things out pretty quick. I'm thinking about setting

up my own but I'm not sure where to begin. Do you have any points

or suggestions? Thank you
Posted by: Stowers - Sunday, April 3, 2016 5:41 AM


Good day! I just would like to give you a big thumbs up for your great information you've got here

on this post. I'll be coming back to your blog

for more soon.
Posted by: Mccrary - Sunday, April 3, 2016 6:45 AM


If some one desires expert view concerning blogging then i suggest him/her

to pay a visit this blog, Keep up the fastidious work.
Posted by: Dobbie - Sunday, April 3, 2016 2:33 PM


Nice post. I was checking constantly this weblog

and I am inspired! Extremely helpful information specifically the remaining

part :) I maintain such information much. I used to be

seeking this certain information for a long time.

Thanks and good luck.
Posted by: Hanran - Monday, April 4, 2016 7:38 AM


Your means of explaining everything in this post is in fact nice, all be able to effortlessly be aware of it, Thanks a lot.
Posted by: Ruckman - Monday, April 4, 2016 11:32 AM


Definitely believe that which you said. Your favorite reason seemed

to be on the internet the easiest thing to be aware of.

I say to you, I definitely get annoyed while people think about worries

that they just don't know about. You managed to hit the nail upon the top and

also defined out the whole thing without having side effect , people could take a signal.

Will probably be back to get more. Thanks
Posted by: Mota - Tuesday, April 5, 2016 6:28 AM


Very nice post. I just stumbled upon your weblog and wanted to say that

I've truly enjoyed browsing your blog posts. In any case I'll be subscribing to

your feed and I hope you write again very soon!
Posted by: Pittman - Tuesday, April 5, 2016 11:42 PM


Valuable info. Lucky me I found your web site by accident, and I am shocked why this accident did not happened in advance!

I bookmarked it.
Posted by: Westfall - Friday, April 8, 2016 11:17 AM


This is the perfect website for anyone who would like to understand this topic.

You realize so much its almost tough to argue with you (not that I really will

need to…HaHa). You certainly put a new spin on a topic which has been discussed for decades.

Excellent stuff, just great!
Posted by: Fulmore - Friday, April 8, 2016 11:49 AM


certainly like your web site however you have to test the spelling on quite

a few of your posts. Many of them are rife with spelling issues and I

in finding it very bothersome to tell the truth nevertheless I will certainly come again again.
Posted by: Dovey - Friday, April 8, 2016 2:24 PM


Admiring the time and energy you put into your website and in depth information you offer.

It's great to come across a blog every once in a while that isn't the same out of date rehashed information. Fantastic read!

I've bookmarked your site and I'm adding your RSS feeds to my Google

account.
Posted by: Duterrau - Friday, April 8, 2016 4:50 PM


Wonderful blog! I found it while browsing on Yahoo News.

Do you have any tips on how to get listed in Yahoo News?

I've been trying for a while but I never seem to get there!

Thanks
Posted by: Magoffin - Saturday, April 9, 2016 2:10 AM


Oh my goodness! Impressive article dude! Thank you so much,

However I am going through issues with your RSS. I don't understand the reason why I am unable to join it.

Is there anybody else having identical RSS

problems? Anyone that knows the solution will you kindly respond?

Thanx!!
Posted by: McDonagh - Saturday, April 9, 2016 11:23 AM


What's up, just wanted to mention, I loved this post.

It was funny. Keep on posting!
Posted by: Deshotel - Saturday, April 9, 2016 12:37 PM


If you wish for to improve your experience simply keep visiting this web site and be updated with the hottest news update posted here.
Posted by: Torpy - Sunday, April 10, 2016 7:26 PM


 









WPL
PUBLISHING CO, INC.
WPL Publishing - 5750 Bou Avenue #1712 - Rockville, MD 20852

Phone: (301)983-0443  -  Fax: (301)983-4367

All Content and Design Copyright © 2026 WPL Publishing
About Us

Contact Us

Privacy Policy

My Account