ConstructionPro Week, Volume: 2 - Issue: 30 - 07/26/2013

When Is a Late Extension of Time Too Late?

By Bruce Jervis

 

When it comes to extending the performance period for excusable delay, the maxim “better late than never” does not necessarily apply. A project owner has an obligation -- express or implied -- to grant extensions in a timely manner. Otherwise, the contractor may be forced to accelerate its pace of work in an attempt to meet the original contract deadline.

 

On a recent federal project, the contractor experienced what appeared to be, and was later ruled, excusable delay. The contractor requested an extension of time. The government refused, insisting on compliance with the original contract deadline and threatening assessment of liquidated damages for late completion.

 

The contractor added equipment and crews. The contractor worked extended hours and paid overtime premiums. Four days before the contract completion date, possibly as a tactic to thwart an acceleration claim, the government granted the requested extension of time. Despite the belated extension, the contractor recovered $1.2 million in acceleration costs.

 

Have you seen situations where project owners defer granting legitimate requests for extensions of time, hoping to keep the project on its original schedule? Do owners sometimes try to game the system, granting extensions only when it seems to provide a tactical advantage? I welcome your comments.

 

COMMENTS

“Have you seen situations where project owners defer granting legitimate requests for extensions of time, hoping to keep the project on its original schedule?”

Yes, and on substantial projects with national architects and construction managers. The market gets wiser each day, however, and IMO such a clumsy maneuver generally tends to occur where the owner has the leverage to brush aside its professional agent’s reservations.

One can easily argue that when any critical path sustains a delay and the duration of the activity then on the path is not extended, completion of the activity is accelerated. Facing an excusable delay that is also a compensable delay, responsible owners will understand they are exposed to either acceleration or delay costs.


Posted by: Frank B. Freeland - Friday, July 26, 2013 11:36 AM


REF: "Timely Time Extensions" paper published in AACE International's COST Engineering journal, May 2011.

http://www.nflaace.org/index_files/timely_time_extensions_j_orr_oct_2010_presentation.PDF
Posted by: John Orr - Friday, July 26, 2013 11:39 AM


 









WPL
PUBLISHING CO, INC.
WPL Publishing - 5750 Bou Avenue #1712 - Rockville, MD 20852

Phone: (301)765-9525  -  Fax: (301)983-4367

All Content and Design Copyright © 2024 WPL Publishing
About Us

Contact Us

Privacy Policy

My Account