A “Force Majeure” clause in fixed-price contracts prohibited a price increase due to natural occurrences. The disclaimer was not limited to delay damages but also applied to escalation in the cost of labor and materials.
When a contract exists between a project owner and a design professional, the owner’s only remedies are under that contract. An owner could not sue its architect for purely economic losses allegedly caused by professional negligence.
Under the terms of a contract, a contractor was entitled to a price adjustment based on actual quantities of work performed. The government could not use a termination for convenience to disregard the contract unit prices and compensate the contractor only for costs plus profit.
Waiver and release forms signed in conjunction with applications for progress payments were not limited to the contractual scope of work. The release applied to claims for extra work and delay damages.